Upper Drainage Erosion Control Improvements
Project Description
The California Department of Transportation (Caltrans) is proposing to replace or repair drainage systems along Highway 9 from Ben Lomond to Highway 35 that have been determined to be deficient. The project would replace and/or reconstruct drainage inlets, install new pipe culverts, fill and abandon old culverts, repair outlets, place rock slope protection, rebuild and lengthen a retaining wall, and repair trail erosion.
Proposed Project Schedule
- Funding Allocation: August 2024
- Advertising: September 2024
- Begin construction: February 2025
- Complete construction: August 2027
Construction Cost
- $8,500,0000